Phase II of boatyard on the way

 

A rendering of the Marine Service Center showing 35 percent of the design of Phase II completed. A 65 percent rendering is expected by the end of the year. (Graphic courtesy Wrangell Harbor Department)

The next step in the renovation process at the Marine Service Center in Wrangell is about to get underway – with better roadways and a paved connection to Trident Seafoods on the horizon.

The section of the MSC nearest to the Case Street gate and Trident’s cold storage, or Project Area 1, would be the first to be renovated, according to Wrangell Harbormaster Greg Meissner.

“The next phase of the project is under design and we have 35 percent of the design finished,” Meissner said. “In November, we should have the additional 65 percent of the design completed. Once that is done and...